AI data centers turn to used jet engines as turbine wait hits six years

Read original source →techcrunch.com

New US gas turbines average six years to deliver, with global orders topping 100 GW against 60-70 GW of annual manufacturing capacity. Converted jet engines can get a data center running in 24 months; xAI installed eight in Mississippi for Colossus 2.